Energy savings cannot be measured directly: they are the energy you did not use. The International Performance Measurement and Verification Protocol (IPMVP) solves this by comparing actual consumption with what the facility would have used without the improvement, the adjusted baseline. It offers four options, A to D, for doing that.

The basic equation

Savings = adjusted baseline energy − reporting-period energy

The baseline is built from data measured before the project. It is then adjusted for changes outside the project's control, such as weather, occupancy or production, so that like is compared with like.

Option A: retrofit isolation, key parameter measurement

Only the equipment affected by the project is measured, and only its key parameter (for example power or operating hours) is measured. Other parameters are estimated and agreed. Option A is simpler and cheaper, but relies on the estimates being fair.

Option B: retrofit isolation, all parameter measurement

The affected equipment is measured completely, usually continuously, for example the full chiller plant's electricity and cooling output. Option B is more accurate than A and is well suited to chiller plants, where the plant can be metered as a system.

Option C: whole facility

Savings are measured from the building's main utility meters, compared with a baseline model of the whole facility. Option C suits projects that affect many systems at once, but small savings can be hidden by other changes in the building.

Option D: calibrated simulation

A computer simulation of the facility, calibrated with measured data, estimates the savings. Option D is used when baseline data is missing, for example in new buildings, or when the effects of measures are hard to separate.

Which option for a chiller plant?

For a chiller plant upgrade or a Cooling-as-a-Service contract, measuring the plant itself (in the spirit of Option B) is usually the clearest approach: plant electricity and cooling output are metered continuously, so the savings belong to the plant, not to unrelated changes in the building.

What a good M&V plan contains

  • The measurement boundary and the option used.
  • The baseline period (at least 12 months of data is good practice) and the baseline model.
  • The adjustments allowed, and how they are calculated.
  • Meters, sensors, accuracy and calibration.
  • Reporting frequency and who can audit the data.